Project Name: New Pump Stations & Terminals in “Abadan” and “Mile 40 Mahshahr Road” Project
Activities: Endorsement of Basic Design Engineering Package, Detailed Engineering, Procurement, Construction, Pre-commissioning and Assistance in Commissioning.
Objective: Objective of this project comprises of expansion, renovation, optimization and upgrading of crude oil & oil products transfer facilities in Abadan and Mile 40 Mahshahr road. The project scope includes the following:
To establish pump stations and storage tanks in Mile 40 Mahshahr road, to transfer received crude oil from Mile 19 to Abadan Refinery with transfer capacity of 210,000 BPD and storage capacity of 528,000 Barrel.To establish pressure adjustment facilities of crude oil from Mile 40, Basreh and Darkhovein in Abadan Refinery, with totally capacity of 670,000 BPD.
To establish common facilities to transfer oil products (Gasoline, Kerosene and Gasoil) and also to establish sending facilities for Fuel Oil and Overhead Distillate separately, and also optimization and construction of relevant pipe lines, totally with capacity of 926,500 BPD as following:
4 pump stations to send products of Abadan refinery to Mahshahr, Ahwaz and Nezamiyeh, with total capacity of 546,500 BPD. Also it is possible to receive & store oil products from Mahshahr facilities via the relevant pump station.Pump station for Overhead Distillate from Abadan to Mahshahr with capacity of 130,000 BPD.Pump station for Fuel Oil from Abadan to Mahshahr with capacity of 250,000 BPD.
Project duration: 36 Month
Partners : Pars Keyhan Company
Client: National Iranian Oil Engineering & Construction Company (NIOEC)