Project name: Abadan Refinery Stabilization and Up-grading Project

Activities: Detailed Engineering, Procurement Services, Procurement, Construction,Pre- commissioning and assistance in commissioning

Objective: Construction of new units with capacity of 210/000 BPD including licensed units (KHT, GHT, SRU, NHT, HCU, CCR, ISOM, HPU) and non- licensed units (CDU, VDU, LPG, ATU, SWS ,Utility and off-site), modification of existing units, overall integration between new and existing units, increasing production of gasoline according to Euro-5 Standard

Project duration: 48 Months

Date of commencement: April 2013

Type of contract: Lump Sum

Location: Abadan

Client: National Iranian Oil Engineering & construction Co.