Project Name: Bandar Abbas Refinery Debottlenecking Project
Activities :
Review and Endorsement of Basic Design Package, Detailed Design, Procurement and Construction.
Objective:
Increasing the capacity of the distillation units of the Refinery from 232,000 BPD to 320,00 BPD.
Project Duration: 24 Months
Type of Contract: EPC
Location: Bandar Abbas
Client : National Iranian Oil Engineering Construction Co.( NIOEC ) .