Project name: Parsi – Aghajari Desalting / Dehydration Plant
Activities:
Engineering, Procurement and Construction (EPC)
Objective:
The purposes of this project are as follows:
- Revamping of existing headers and manifolds and installation of 2 stage separators (2nd and 3rd) in PARSI DAREH – NEY Production unit and providing related facilities such as pump station and chemical injection facilities and 24.5 km pipeline for transferring salty crude oil to KARANJ production unit separately.
- Revamping of existing headers and manifolds in PARIS CLASTER well heads after 1st stage separation.
- Revamping the inlet headers and designation of 2 stage separators (2nd and 3rd) for salty crude oil in KARANJ production unit.
- Installation of a new desalting plant with capacity of 110,000 BPD and also waste water treatment facilities beside to KARANJ production unit.
Project duration: 30 Months
Type of contract: EPC
Location: Aghajari-Ahwaz
Client: National Iranian South Oil Fields Company (NISOC)